The Shop Building continues to come together, as we completed its structural steel and base plate installation, with roofing to begin on the structure soon. The Food Pavilion will begin installation of structural steel in the near future, while Pier 2's deck work will continue. Additionally, the cutting and lifting of Shipwright's Cottage is anticipated to begin late this week or early next week.

Please note that weekend work will be occurring on September 16 and 23. We apologize for the inconvenience and appreciate the community’s support on this once-in-a-generation environmental justice project.