More features are rising from the shore at 900 Innes, as we placed the main eight structural columns at the Shop Building! Additionally, we formed the slab for the Food Pavilion, with waterproofing work and utility installation upcoming. We also completed excavation and have began installing marine rails.

Finally, we're excited to share that the shoring of Shipwright's Cottage is anticipated to begin in the coming week. Stay tuned for more photos of this work.